Salient Features :
Setting up of Compact/packaged Sewerage Treatment Plant (STP) at:
(1) Avanti Bai Hospital (10 KLD) - Completed
(2) Balrampur Hospital (760 KLD) - WIP
treatment Reuse of waste water (sewerage) generated by hospitals. -Treatment plant is based on Sequential Batch Reactor (SBR) technology. - Improvement of existing toilet in the premises. - BOD (biological oxygen demand) in treated water is less than or equal to 10 PPM -Reuse of treated water will save electricity and ground water.
Status of work at Balramapur Hospital:
a. STP of 10 KLD has been completed at Avantibai Hospital and same has been inaugrated on 13.09.2019. b. Balrampur Hoapital 760 KLD work is in progress:
1. Equalization Tank- Completed
2. Intermediate Tank- Completed
3. SBR Tank -1- Erection Completed
4. SBR Tank -2- Erection Completed
5. Treated Water Sump-Civil Work Completed upto90%
6. Fabrication work of SBR tank is in progress. Expected to be completed by 30.09.2020 M/s DNP Infrastructure Ramanuj (Ph: 9979849426)