Name of Contractor Total Cost Start Date Physical Progress (%) Financial Progress (SCM)
M/s DNP Infrastructure 6.12 30.09.2020 60% 1.6

Salient Features :

Setting up of Compact/packaged Sewerage Treatment Plant (STP) at:

(1) Avanti Bai Hospital (10 KLD) - Completed

(2) Balrampur Hospital (760 KLD) - WIP

treatment Reuse of waste water (sewerage) generated by hospitals. -Treatment plant is based on Sequential Batch Reactor (SBR) technology. - Improvement of existing toilet in the premises. - BOD (biological oxygen demand) in treated water is less than or equal to 10 PPM -Reuse of treated water will save electricity and ground water.

Status of work at Balramapur Hospital:

a. STP of 10 KLD has been completed at Avantibai Hospital and same has been inaugrated on 13.09.2019. b. Balrampur Hoapital 760 KLD work is in progress:

1. Equalization Tank- Completed

2. Intermediate Tank- Completed

3. SBR Tank -1- Erection Completed

4. SBR Tank -2- Erection Completed

5. Treated Water Sump-Civil Work Completed upto90%

6. Fabrication work of SBR tank is in progress. Expected to be completed by 30.09.2020 M/s DNP Infrastructure Ramanuj (Ph: 9979849426)


Before ImageAfter Image